In the recent case of Davies v Moreland CC & Anor [2012] VCAT 532 the Tribunal considered an application for an enforcement order to prevent the installation of a Smart Meter on a home within a Heritage Overlay.

The Tribunal dismissed the application on two grounds. The installation of a smart meter was routine maintenance which did not require a planning permit. Further the installation of the Smart Meter did not trigger a permit because it would not change the appearance of a heritage place.

The case provides a good analysis of the concept of "works" under the Planninng and Environment Act 1987.

About the Author

Miguel Belmar

Recent Posts

TRIBUNAL CONSIDERS ITS JURISDICTION TO REVIEW 173 AGREEMENT

Miguel Belmar Date: 25-03-2015

ANOTHER ROOF TOP. A DIFFERENT RESULT.

Miguel Belmar Date: 05-03-2015

ROOFTOP TERRACE REPLACED WITH?…AN APARTMENT.

Miguel Belmar Date: 23-02-2015

VCAT confirms its role is not to find a more suitable site.

Miguel Belmar Date: 03-02-2014

PLANNING AND THE VICTORIAN CHARTER OF HUMAN RIGHTS

Miguel Belmar Date: 06-06-2013

Latest on harm minimisation in liquor licensing

Miguel Belmar Date: 07-01-2013